Period Optimization Scheme Determination of Building Engineering Construction Network Plan
-
摘要: 以工期优化基本原理和网络计划工作总时差性质为基础,对关键线路和次关键线路进行比较,设计出工期优化的所有可行方案,为进一步根据工程质量控制目标、投资控制目标和资源供应条件求得最佳方案提供技术路线。Abstract: Based on the period optimization basic principal and the total time difference features of network plan job,in order to get to supply technique route to the best scheme amd according to the engineering quality target,investment control target and resource supply,the key route and the vice-key route are compared to design all feasible period optimization schemes.
-
-