    • 摘要: 使用ANSYS软件构建了与宝泉下水库大坝加高施工对应的有限元模型,在考虑不同的蓄水方式与新老坝体不同弹性模量的基础上,分析了不同蓄水位和弹性模量对坝体位移、应力的影响。

       

      Abstract: This paper establishes FEM related to the Baoquan lower reservoir dam heightening construction by using ANSYS software. Based on considering different storage water methods and different elastic modulus of old and new dam bodies, it also analyzes the effect of different storage levels and elastic modulus to the dam body displacement and stress.

       

    /