贵州脚里水库可研阶段施工组织设计

    Construction Management Designs in the Feasibility Study Stage for Jiao-Li Reservoir Project

    • 摘要: 贵州省脚里水库工程采用隧洞导流、围堰一次拦断河床的导流方式。施工组织设置沙石加工、混凝土生产、钢筋板加工和综合加工等施工辅助系统。在可研阶段,对施工导流方式、主体工程施工方案、施工总布置和总进度进行了优化,缩短了施工计划工期,提高了工程质量保障。

       

      Abstract: Jiao-Li reservoir dam is MgO concrete asymmetric parabola double curvature arch dam with 46.5m high.The key techniques of reservoir project construction management designs in the feasibility study stage are in the depth analysis, the construction diversion method, major structures construction scheme,general construction layout and construction master schedule are proposed.Adopting the successive section cofferdam and diversion tunnel flow river diversion scheme, sand processing, concrete production,comprehensive processing and other construction auxiliary systems are putted-up in the project construction general layout.After the optimal design, the total construction is proposed to 22months, which will shorten the construction progress, improve the construction quality, and get good designing effects.

       

    /