湖北咸宁核电站场平工程原位直剪试验研究

    Study on Xianning Nuclear Power Station Field-leveling Engineering In-situ Direct Shear Test of Hubei Province

    • 摘要: 结合湖北咸宁核电站场平工程,从试点的选择、试件制备、试验布置、设备安装、荷载施加等方面探讨了水平推挤法试验的关键步骤。根据试验记录和现场资料,得出了抗剪强度参数,绘制了土体破坏剪切压力与位移的关系曲线。

       

      Abstract: Combined with Hubei xianning nuclear power station field-leveling engineering,this paper discusses the key steps in thrust and shear test from the aspects of test site selection,test material preparation,test arrangement,equipment installation,load application,etc.According to the test record and field data,it obtained the shear strength parameters and drew the relation curve of soil destruction of shear stress and displacement.

       

    /