山西泽城西安水电站(二期)工程施工导流方案研究

    Study on Zecheng Xi'an Hydropower Station(Phase II)Engineering Construction Diversion Scheme in Shanxi Province

    • 摘要: 针对山西泽城西安水电站二期工程的特点,根据《水利水电工程施工组织设计规范》(SL303-2004)确定了该工程大坝施工的导流标准,提出了全年10年一遇洪水标准,非汛期10年一遇洪水标准、坝体过水,非汛期10年一遇洪水标准、坝体不过水3个导流方案,并对这3个导流方案进行了比选,最终确定采用枯水期坝体不过水的导流方案。

       

      Abstract: Aimed at the characteristics of the second phase of Xi'an hydropower station,and on the basis of the Specifications for Construction Planning of Water Resources and Hydropower Engineering(SL303-2004),this paper determined the diversion standards of the dam construction project,and came up with three diversion schemes:once-in-a-decade flood standard for all year round,once-in-a-decade flood standard for non-flood season and the water flow through the dam body,once-in-a-decade flood standard for non-flood season and the water doesn't flow through the dam body,and then makes comparison and selection of these three schemes and finally determined using the non-flood season and the water doesn't flow through the dam body.

       

    /