缅甸THA-HTAY水电站竖井与闸室贯通施工技术分析

    Analysis on Burma THA-HTAY Hydropower Station Shaft and Chamber Cut-through Construction Technique

    • 摘要: 针对缅甸THA-HTAY水电站工程特点及其竖井与闸室贯通施工方案,探讨了竖井下部及中心段导流洞的加固处理,贯通段的开挖、支护、混凝土衬砌等施工工艺。

       

      Abstract: According to the Burma THA-HTAY hydropower station construction features and the surrounding rock condition of shaft and chamber,it analyzes its shaft and chamber cut-through construction scheme,discusses the reinforcement treatment of shaft bottom and center section pilot tunnel,the excavation,support,concrete lining and other construction technology of cut-through section.

       

    /

    返回文章
    返回