Study on Zecheng Xi'an Hydropower Station(Phase II)Engineering Construction Diversion Scheme in Shanxi Province
-
Graphical Abstract
-
Abstract
Aimed at the characteristics of the second phase of Xi'an hydropower station,and on the basis of the Specifications for Construction Planning of Water Resources and Hydropower Engineering(SL303-2004),this paper determined the diversion standards of the dam construction project,and came up with three diversion schemes:once-in-a-decade flood standard for all year round,once-in-a-decade flood standard for non-flood season and the water flow through the dam body,once-in-a-decade flood standard for non-flood season and the water doesn't flow through the dam body,and then makes comparison and selection of these three schemes and finally determined using the non-flood season and the water doesn't flow through the dam body.
-
-